Question 1: Project metrics
Pick two of the three project aspects described below,
and describe metrics that would
provide relevant information for that aspect of a project,
how you would gather those metrics,
and any potential weaknesses in the approach you have suggested:
- Area I: Progress metrics: allowing you to
track how well the project is adhering to both its schedule requirements
and its cost requirements, and update projected times/costs.
- Area II: Quality metrics: allowing you to
track how well the project is adhering to its quality requirements.
- Area III: Requirements stability metrics:
allowing you to
assess the magnitude and impact of changes to project requirements.